E s t i m a t e d |
| Area / Description |
Contact Person |
Start
date: |
Completion
date: |
| Rec Plex: |
|
|
|
| Upgrade Restrooms by mailboxes for ADA access |
Rich Bretz |
7/1/09 |
9/1/09 |
| St. Francis Chapel roof truss repair |
Rich Bretz |
8/3/09 |
8/20/09 |
| Pool painting |
Bernie Beyer |
7/27/09 |
8/21/09 |
| Auxiliary Gym renovation for Wrestling Team |
Rich Bretz |
6/15/09 |
9/1/09 |
| |
|
|
|
| Dolan Science Center: |
|
|
|
| E117/18 renovation for painting classroom |
Rich Bretz |
7/1/09 |
9/1/09 |
| Fume Hood recertification |
Bernie Beyer |
TBD |
|
| |
|
|
|
| Library: FTIC renovations |
Rich Bretz |
7/1/09 |
9/1/09 |
| |
|
|
|
| Green Road Annex: parking lot drainage project |
|
|
|
| |
|
|
|
| Dolan Hall: |
|
|
|
| new upper roof |
Bernie Beyer |
TBD |
TBD |
| community kitchen renovation & re-carpet corridors |
Mike Roeder |
TBD |
TBD |
| |
|
|
|
| Hamlin Hall: new flat roofs |
Bernie Beyer |
7/1/09 |
|
| |
|
|
|
| Millor Hall: brick repairs |
Rich Bretz |
7/15/09 |
TBD |
| |
|
|
|
| Murphy Hall: standpipe design and installation |
Rich Bretz |
6/1/09 |
9/1/09 |
| |
|
|
|
| |
|
|
|
| General Campus / Quad areas: |
|
|
|
| Sidewalk repairs - in front of Pacelli |
Rich Bretz |
7/1/09 |
7/15/09 |
| Belvior Lot striping |
Rich Bretz |
TBD |
TBD |
| Pacelli Lot - pavement repairs |
Rich Bretz |
TBD |
TBD |
| Steam Tunnel and Piping repairs - various locations |
Bernie Beyer |
5/15/09 |
TBD |
| Murphy / Sutowski heating loop upgrades |
Bernie Beyer |
TBD |
TBD |
| Occupancy sensor and hand dryer installations |
Bernie Beyer |
5/15/09 |
on going |
| |
|
|
|
| |
|
|
|